Third Progress Report 4 October 2013

The Third Progress Report was sent to the Inspector on 7 October 2013 together with a Progress Report from Enfusion and a revised Programme Plan.

Response from the Planning Inspector, David Hogger

The Inspector has noted the up-date with regard to progress on the Local Plan (Progress Report 3) and is pleased that the timetable continues to be met.